| |
Best Estimate Challenge Winner:
The Northern Arizona University Union Dining Hall
by Kinney Construction Services
Sponsored by Design Cost Data Magazine and the International Builders Exchange
Executives
By Lynn Murray
|

Kinney Construction Services won the
Best Estimate Challenge with their submittal of the new Northern
Arizona University Union Dining Hall project.
|
|

The new dining hall at NAU included
over 23,000 square feet of new construction and 4,140 square feet of
renovations to the existing Union Building on NAU's central campus.
|
|

The new dining hall and renovations
to the existing Union building was completed in 13 months, in time
for the start of classes in Fall 2008. |
Recipe for Success
Creating a state-of-the-art dining facility to satisfy more than 22,000 hungry
college students would serve up a challenge for any university. But long before
starving scholars began to stretch their dining dollars at Northern Arizona
University’s Union Dining Hall, the estimating team of Kinney Construction
Services Inc. (KCS) cooked up some careful calculations of its own.
The 27,283-square-foot expansion project was completed in just 13 months – in
time for the start of classes in Fall 2008. And keeping it within the $8.05
million budget proved to be a recipe for success for KCS.
Design Cost Data™, along the International Builders Exchange Executives and the
American Society of Professional Estimators (ASPE), is proud to announce Kinney
Construction Services of Flagstaff, Ariz., as the winner of the 2009 Best
Project Estimate Challenge, for its work on the North Arizona University (NAU)
Union Dining Hall project.
This one-of-a-kind challenge – kind of a “closest to the pin” competition for
the estimating community – was intended to recognize the estimating team that
produced an estimate that hits right on. Projects were evaluated on estimate vs.
actual costs, the estimating process and the final presentation of the project.
KCS estimated $8,049,916 for the project, including a minimal contingency of
just 2.3 percent of the project total, or $186,280. The final contract amount
was not adjusted by any change orders. All construction cost estimates were spot
on. But containing costs didn’t mean cutting corners.
“I expected nothing short of spectacular for this highly anticipated facility,
and KCS delivered phenomenally in all areas,” said Jan Kuhn, associate
vice-president for enrollment management and student affairs at NAU.
The Project
The NAU Union Dining Hall expansion project consisted of 23,143 square feet of
new construction and 4,140 square feet of renovations to the existing Union
building on NAU’s central campus. New construction included adding a modern,
two-story building that supports dining and common areas, as well as multiple
food service vendors, and the construction of a complex curtain wall system.
Renovations included the installation of a commercial kitchen and bringing the
building up to code with NAU’s technical standards.
|

The project included adding a modern,
two-story building that supports dining and common areas, as well as
multiple food service vendors. |
KCS had previously completed several other projects for the 110-year-old
university, but this one began a bit differently. The contract delivery method
was Construction Manager at Risk (CMAR), which entails a commitment by the
construction manager to deliver the project within a Guaranteed Maximum Price (GMP).
The manager acts as consultant to the owner in the development and design
(pre-construction) phases, but as a general contractor during the construction
phase.
The Dining Hall project was originally awarded to another CMAR bidder, who did
not perform acceptably during the pre-construction phase. KCS was called in to
take over the project, working with Phoenix-based design team of OWP/P
Architects Inc. of Chicago.
“KCS confidently and successfully took on the challenging task of completing all
pre-construction services with 30 days of selection. Their final GMP was
provided in time for Arizona Board of Regents approval, was within the
university’s budget and was more than $1,000,000 below the original budget
proposal,” said Kuhn.
The pre-construction and procurement schedule was set and inherited by KCS –
which meant tight deadlines and high expectations. KCS embraced the challenge,
completing the value engineering and constructability studies; securing all
subcontractor proposals; and beginning work just 21 days behind the original
proposed schedule.
The Process
Once KCS was brought on to the project, the first estimating task was to pull
together an initial budget on the most recent set of contract documents. The
firm reviewed the plans and specifications in order to understand what types of
materials, systems and means of construction were required for the project.
Next, subcontractors were contacted to obtain unit costs and “ball-park”
figures. Detailed take-offs were then completed for most systems, including
concrete foundations and slabs, glazing/curtain walls, roofing, drywall/metal
stud wall and ceiling systems, electrical and plumbing. A combination of
subcontractor feedback, recent project experience and “gut instinct” proved a
strong formula for arriving at budget estimates for each item.
“Their ability to get a quick response from subcontractors, over a weekend,
indicates a good working relationship, which is the critical element in general
contractor estimating today,” said Kris Larson, CPE, senior estimator,
Construction Control Corp. of Salt Lake City, Utah, who helped judge the Best
Project Estimate Challenge.
The project was far from ordinary. The university had created a previous system
of underground utilities (since abandoned) that required removal of abandoned
pipes and conduits beneath the centrally located project site.
The foundation of the project was 62 drilled caissons buried to an average depth
of 16 feet. The geotechnical excavation indicated that KCS drill into solid rock
for 2 feet, but that proved incorrect, requiring contingency dollars be used for
additional hard rock excavation and more concrete for caissons.
|

Project Team from left to right: Mike
Thomas, Project Manager, LEED AP; Andrew Iacona, Project Engineer &
Safety Program Director; Tyler Smith, Superintendent; Tim Kinney,
President, LEED AP; and Charlie Hawken, Superintendent. |
The first floor, designed to be an exposed concrete floor, had to be protected
throughout the construction process. Pouring was delayed until the roof
structure was complete and the second floor deck was poured, to eliminate
traffic on the finished slab.
Mechanical systems were not complicated but were custom-made due to unique shape
requirements, including a 28-inch exposed spiral duct that ran the length of the
building.
The addition connected to existing buildings, with floor heights of each
building being different. Complicating factors included outdated life safety
systems in existing buildings and a joint expansion system to allow the new
building to move independently of the existing buildings.
The project required coordination with six food service vendors regarding
supplies and installation of their products.
The Team
The KCS project lead team consisted of Tim Kinney, president, LEED AP; Mike
Thomas, project manager, LEEP AP; Andrew Iacona, project engineer and safety
program director; and Charlie Hawken and Tyler Smith, superintendents.
“Communication, experience and organization are three essential elements that,
when executed properly, result in exceptional construction quality,” said
Thomas. “An experienced onsite crew, coupled with strong office administrative
support, significantly contributed to the success of this project.”
|

Kinney Construction Services worked
closely with subcontractors, listened to subcontractor feedback, drew
upon past project experience and listened to their 'gut instinct' to
arrive at budget estimates for each job item for the NAU project. |
The Client Agrees
“KCS operated as a truly collaborative CMAR partner. They kept NAU informed and
involved throughout the project, provided solutions to challenges, met extreme
schedule and budgetary constraints, and always operated in the best interest of
the university,” said Kuhn.
“We accomplished this challenge within the desired contract schedule, without
any change orders, without reducing scope, with a high level of quality and
within budget,” said Thomas. “And we had fun doing it.”
The Northern Arizona University’s Union Dining Hall project submittal and the
Best Estimate Challenge Runner Up, The Westin Book Cadillac Hotel & Condominiums
submitted by Marous Brothers Construction and Jenkins Construction, Inc., a
joint venture will be on display at the upcoming American Society of
Professional Estimators’ 2009 Conference July 22-25 in St. Louis, Mo. Patsy
Smith, Interim Executive Director of ASPE will accept $1,000 from Design Cost
Data for the ASPE National Scholarship Fund and she will also present ASPE
Phoenix Chapter No. 6 a matching $1,000 from the International Builders Exchange
Executives (www.bxnetwork.org)
in KCS’ honor for Chapter No. 6’s Scholarship Fund at the conference.
|