Montgomery
County Detention Facility
Architect
Goodwyn, Mills and Cawood, Inc.
2660 East Chase Lane, Montgomery, AL 36117
www.gmcnetwork.com
General Description
Location: Montgomery, Alabama
Date Bid: Sep 2006 Construction Period: Oct 2006 to Nov
2009
Total Square Feet: New construction, 168,998; Renovation,
approximately, 18,000; total, 186,998. Site: 6.15 New/3.25 Existing.
Number of Buildings: Two.
Building Size:
Existing Facility:
Basement, 17,003; first floor, 18,570; second floor, 18,710; third and
fourth floor, 18,686; total, 91,654; Addition to Existing Facility,
Basement, 1,071; first floor, 1,367; second floor, 1,892. Approximately
18,000 renovated.
New Facility:
First floor, 41,416; second floor, 41.250; third & fourth floor, 43,166;
total 168,998; total of renovation and new construction, 186,998 square
feet.
Building Height:
Existing Facility:
Basement, 148; first floor, 148; second floor, 228; third and
fourth floor, 228;floor to floor, 228;; total, 974; Addition to
Existing Facility, Basement, 148; first floor, 202; second floor,
158; total, 506.
New Facility:
First floor, 16; second floor, 22; third floor, 22; fourth floor,
24; floor to floor, 228; total 862.
Basic Construction Type: Renovation/Addition/New/Concrete
Frame/Structural Steel.
Foundation: Cast auger piles, cast-in-place, slab-on-grade.
Exterior Walls: Architectural metal panels, precast. Roof:
TPO. Floors: Concrete. Interior Walls: CMU, metal stud
drywall.
Projected and/or modeled energy usage: 113.5 KBTU/SF/Yr
Construction Team
Owners Representative: T.C.U. Consulting - P. O. Box 230487,
Montgomery, AL 35117
Structural Engineer:
New Facility:
Facility Design Group - 2233 Lake Park Drive, Smyrna, GA 30080
Existing Facility:
Grant Engineering - 325 Hull Street, Montgomery, AL 36104
General Contractor: Bell and Associates - 255 Wilson Pike Circle,
#200, Brentwood, TN 37027
Mechanical Engineer:
New Facility:
Facility Design Group - 2233 Lake Park Drive, Smyrna, GA 30080
Existing Facility:
MW Davis Dumas and Associates - 2720 3rd Avenue South, Birmingham, AL
35233
Electrical Engineer:
New Facility:
Facility Design Group - 2233 Lake Park Drive, Smyrna, GA 30080
Existing Facility:
Jackson Renfro & Associates, Inc. - 141 Village Street, #1, Birmingham,
AL 35242
Landscape Architect: Goodwyn, Mills and Cawood, Inc. - 2660 East
Chase Lane, Montgomery, AL 36117
The Montgomery County Commission hired Goodwyn, Mills and Cawood to
design the new state-of-the-art Montgomery Detention Facility located in
Downtown Montgomery, Ala. The massive structure opened in September 2009
and inmates were moved into it in October 2009. The existing structure,
built in the 1980s, was overcrowded and at capacitythe structure was
housing almost twice as many inmates as planned for. In order to
maximize the budget allocated, GMC renovated the original facility and
added a new building to house an additional 696 prisoners. The existing
kitchen and laundry spaces were completely overhauled to accommodate the
increased inmate population. The old structure is now used for
maximum-security prisoners as it is fitted with the appropriate cells
for them.
The design contains approximately 170,000 square feet of new
construction and approximately 18,000 square feet of remodeled existing
space. The new facilities include a 696-bed facility built on the
property across the street from the existing jail. A pedestrian walkway
connects the two buildings over McDonough Street, complete with a new
elevator and stair tower attached to the existing detention facility.
Designed with security in mind, the housing unit utilizes panelized
steel cells arranged in multi-level pods around a dayroom that is
overlooked by a central control booth. In addition a vehicular sally
port, intake transfer and release, administration, master control,
medical, and command center spaces are incorporated into the design.
Intricate electrical and mechanical systems are also included due to the
nature of the facility.
Product Information
Concrete Sealer: Ashford (Turner Baxter installer)
Drywall: United States Gypsum
Elevators: Otis Entrances & Storefronts: Kawneer
Flooring: Nora, AZROCK
Lighting: Lithonia Paint: Sherwin Williams
Protective Film: Enpro Distributing, Inc.
Roofing: Firestone
Windows: C M Security Group
Wall & Corner Protection: InPro Corporation
Wall Panels: Protean Construction Products, Inc.: FM-200
Insulated Wall Panels - 22 gage galvanized steel with smooth and Aztec
embossed texture on 2-inch and 3-inch urethane foam core and one custom
Khaki Shade high and low gloss Kynar paint finish. FM-230 Insulated
Profile Panels - 22 gage galvanized steel on
2-inch profiled urethane foam core with one standard Dark Bronze Kynar
paint finish.
www.protean.com
|
|

|