Grandville Police & Court Facility Architects MHB Paradigm Design Group, Inc.
550 3 Mile Road, N.W., Grand Rapids, MI 49544
www.mhbparadigmdesign.com
Location: Grandville, Michigan Total Square Feet:
32,100 Construction Period: June 2000 to Aug 2001
Construction Team
Structural Engineer: Soils & Structures, Inc. - 6480 Grand Haven Road, Muskegon, MI 49441
Electrical & Mechanical Engineer: Engineering Design Group - 3000
Ivanrest, #A1, Grandville, MI 49418
Landscape Architect: MHB Paradigm Design Group, Inc. - 550 3 Mile Road, N.W., Grand Rapids, MI 49544
Cost Estimator: C.D. Barnes Associates, Inc. - 3437 Eastern Avenue, S.E., Grand Rapids, MI 49508
The Grandville Police & Court Facility was a phased project that required keeping the Court and Police Department in full and complete operation during the entire project. The work consisted of removing the existing Firebarn and the upper portion of part of the building, and erecting a new addition and shell. This phase had to be completed during the winter. Both departments were then moved into the new area while the balance of the building was demolished to the concrete slab and a new masonry/metal stud building was erected and finished. At this time, the Police Department could be moved into their new quarters, leaving the Court to occupy their space from Phase One.
Special problems included keeping the 911 number and other communication lines in operation at all times. The Court and Police Dispatch were able to stay undisturbed in Phase One and then moved into the new quarters. The Police Department was moved into part of the Court area while their new area was being built, and then were moved into the new area upon completion. The parking lot was also rebuilt and relocated while providing maximum parking and building access at all times.
Manufacturers/Suppliers
DIV 04: Masonry: The Belden Brick
Company.
DIV 07: Standing Seam Roof: RollCOM; Translucent Panels: Major
Industries.

|